Final Payment for Water Carbon Dioxide System Upgrades

Appleton, WIMonday, November 9, 2026contractsutilitieswater

In plain English

Contract 154-24 was awarded to Rhode Brothers Inc. for $208000. Change orders added $4549. The final contract amount is $212549 with payments to date of $198364.72. The committee is asked to approve the final payment of $5086.28.

Why it matters: This affects the cost and completion of water system upgrades paid for by city funds.

Original agenda text

Contract 154-24 was awarded to Rhode Brothers, Inc. for Water Carbon Dioxide Chemical Storage System Upgrades for $208,000 with a contingency of $20,800. Change orders were approved totaling $4,549. Final contract amount is $212,549 with a contingency of $16,251. Payments issued to date total $198,364.72. Request final payment of $5,086.28.

Exactly as published by Appleton · File 26-1446 · Report Action Item · Agenda item 10.

Explain it in more detail

Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.

Go Pro

Get an email the day Appleton posts an agenda that mentions your street or topic. Pro, $9/mo, cancel any time.

Or start with one free weekly alert

Related items in Appleton

Nov 9, 2026 Finance Committee

Final Payment for Unit Z-26 Water Reconstruction

Contract 87-26 was awarded to Kruczek Construction for $546000. Payments issued so far total $444492. The committee is asked to approve a final payment of $48742.60 for a total paid of $493234.60.

contractsutilitieswater