In plain English
The court is asked to approve awarding a contract to LASS Engineering and Construction, Inc. for $5,976,750 for general watershed repairs to several channels and reservoirs. This is for the Flood Control District from December 1, 2026 to November 30, 2027 with four one-year renewal options. The MWBE goal is 22 percent.
Why it matters: This affects flood protection for residents near Spring Creek, Cypress Creek, Little Cypress Creek, Barker Reservoir, Addicks Reservoir, and Willow Creek.
Places mentioned: Spring Creek; Cypress Creek; Little Cypress Creek
Explain it in more detail
Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.
Nov 19, 2026 Commissioners Court
The court is asked to approve an interlocal agreement with the University of Houston for $99,286. The agreement is for a countywide soils management study that focuses on establishing soil microbiology. It applies countywide.
contractsenvironment
Nov 19, 2026 Commissioners Court
The court is asked to approve an agreement with Carollo Engineers, Inc. for $2,000,000. The company will provide on-call Owner’s Advisor Professional Services. These services support progressive design-build procurement and...
contractsenvironment
Nov 19, 2026 Commissioners Court
The court is asked to approve an escrow agreement with JP Morgan Chase Bank, N.A. This is in connection with a Texas Water Development Board grant for the SAFER Study. The agreement lets the Flood Control District deposit funds...
contractsenvironment
Nov 19, 2026 Commissioners Court
The court is asked to approve awarding a contract to Northtex Construction, LLC for $16,259,518 to build the Friendswood Regional Stormwater Detention Basin. The County Clerk would sign any bonds. This is for the Flood Control...
contractsenvironment