Amended Agreement for Charles Anderson Bridge

Pittsburgh, PATuesday, November 10, 2026transportationcontracts

In plain English

This resolution amends a previous agreement for the Charles Anderson Bridge project. The total cost increases by $6,335,000 to $70,016,632 for the construction phase. This resolution only approves the amended reimbursement agreement.

Why it matters: This affects drivers, cyclists, and pedestrians who use the Charles Anderson Bridge.

Original agenda text

Resolution amending Resolution 821 of 2025 which provided for an amended Reimbursement Agreement or Agreements with the Pennsylvania Department of Transportation for costs associated with the Preliminary Design, Final Design, Right-of-Way, and Construction phases of the Charles Anderson Bridge project; providing for the payment of the costs thereof, not to exceed Seventy Million Sixteen Thousand Six Hundred Thirty-Two Dollars ($70,016,632.00), an increase of Six Million Three Hundred Thirty-Five Thousand Dollars ($6,335,000.00) for costs associated with the Construction phase of the project from the previously executed agreement. This resolution serves to authorize only the amended Reimbursement Agreement or Agreements, at a cost not to exceed Seven Thousand One Hundred Dollars ($7,100.00), an increase of Zero Dollars ($0.00) from the previously executed agreement for costs associated with the Preliminary Design, Final Design, and Right-of-Way phases of the project. Future Resolutions will authorize the project specific service agreements.

Exactly as published by Pittsburgh · File 2026-1076 · Resolution · Agenda item 25.

Explain it in more detail

Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.

Go Pro

Get an email the day Pittsburgh posts an agenda that mentions your street or topic. Pro, $9/mo, cancel any time.

Or start with one free weekly alert

Related items in Pittsburgh

Nov 18, 2026 Standing Committees

Reimbursement agreement for Smithfield Street design costs

This resolution sets up a reimbursement agreement with the Pennsylvania Department of Transportation. It covers preliminary design costs for the Smithfield Street Phase 2 project from Fort Pitt Boulevard to Forbes Avenue up to...

transportationcontracts
Nov 17, 2026 City Council

Amended Agreement for Charles Anderson Bridge Project

This resolution amends a prior agreement with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project. It increases the total amount by $6335000 for a new total not to exceed $70016632. This...

transportationcontracts
Nov 17, 2026 City Council

Amended Construction Contract for Charles Anderson Bridge

This resolution amends an agreement with Mosites Construction Company for the Charles Anderson Bridge project. The new total cost is not to exceed $60271782.07 which is an increase of $11794005.07. The costs are 100 percent...

transportationcontracts