In plain English
This resolution would approve an agreement with A. Merante Constructing Inc. for the construction phase of the Pittsburgh City Steps project. The cost is not to exceed 6,494,897 dollars and 70 cents and is reimbursable at 100 percent.
Why it matters: This affects people who use the city steps for walking by paying for the actual construction work.
Explain it in more detail
Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.
Nov 17, 2026 City Council
This resolution lets the mayor and the Department of Mobility and Infrastructure sign or change a grant agreement with the U.S. Department of Transportation for the RAISE Hill District Project. There is no cost to the city.
contractstransportation
Nov 17, 2026 City Council
This resolution updates an agreement with the Pennsylvania Department of Transportation for the Charles Anderson Bridge project. It increases the total to 70,016,632 dollars (up 6,335,000 dollars) for the construction phase. This...
contractstransportation
Nov 17, 2026 City Council
This resolution updates the agreement with Mosites Construction Company for building the Charles Anderson Bridge. The new total is not to exceed 60,271,782.07 dollars (up 11,794,005.07 dollars) and is 100 percent reimbursable.
contractstransportation
Nov 9, 2026 City Council
This resolution would approve a supplemental agreement with TRC Engineers Inc. for the construction phase of the Pittsburgh City Steps project. The cost is not to exceed 1,448,949 dollars and 42 cents.
contractstransportation