Amendments for Intake Reception Center Expansion Project
In plain English
The board may approve changes to a design contract with Nacht and Lewis Architects that add work to separate utility systems and raise the contract amount by $70,350. The board may also increase the contingency amount in the construction contract with ProWest PCM by about $72,638. The director of General Services could approve change orders up to the new contingency total.
Why it matters: This affects the county jail and Intake Reception Center project in the Second District and the companies doing the design and construction work.
Original agenda text
Consider recommendations regarding the Amendments to Design Contract with Nacht and Lewis Architects and Construction Contract with ProWest PCM, Inc. for the Intake Reception Center (IRC) Expansion and ADA Improvements Project, Second District, as follows: (4/5 Vote Required)
a) Approve and authorize the Chair to execute Amendment No. 3 to the Professional Services Agreement (BC21261) with Nacht and Lewis Architects, Inc. to: (i) to provide design, engineering, cost estimating, specifications, drawings, and construction administration support necessary to separate the Main Jail and IRC mechanical, electrical, and plumbing utility systems from each other as part of IRC Expansion and ADA Improvements Project to the scope of services; and (ii) increase the maximum compensation under the Agreement from $2,129,659.00 to $2,200,009.00 (a total increase of $70,350.00);
b) Approve and authorize the Chair to execute Amendment No. 1 to Board Contract SCON-003468 with ProWest PCM, Inc. (Agreement) for the construction of the IRC Expansion and ADA Improvements Project No. PRJ-000124 (Project 20041) (Project) increasing the contingency amount by $72,637.91, for an amended contingency amount of $386,350.21;
c) Approve and authorize the Director of General Services, or Assistant Director, to approve Change Orders under the Agreement in an aggregate amount not to exceed $386,350.21;
d) Determine that recommended action a) is exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Sections 15262 and 15378(b)(4), as the actions involve planning, funding, procurement, and other governmental fiscal and administrative activities that do not constitute approval of a project or commit the County to a specific course of action that may result in a physical change to the environment; and
e) Determine that recommended action b) continues to be exempt from the provisions of CEQA Guidelines Section 15162, no substantial changes are proposed to the project as covered by the Notice of Exemption (NOE) (GSD-030624-20041-0001) approved and adopted by the Board for this project on March 6, 2025 NOE, and no new information of substantial importance has come to light regarding environmental effects of the project or of the sufficiency or feasibility of mitigation measures, and therefore these actions are within the scope of the NOE, and determine that therefore no new environmental document is required.
Exactly as published by Santa Barbara County · File 26-01041 · Administrative Item · Agenda item 33.
Explain it in more detail
Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.