Change Order for Project UR-26-A1
This adds $12,500 to the contract. It also extends the substantial completion date to November 6, 2026 and the final completion date to November 20, 2026.
This adds $31,746.32 to the contract for the improvement district project.
Why it matters: This changes the cost of work that will affect property owners in the district.
Change Order No. 1 in the amount of $31,746.32 for Improvement District No. BN-25-F1.
Exactly as published by Fargo · File 23-4958 · Consent Agenda · Agenda item 18.
Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.
Get an email the day Fargo posts an agenda that mentions your street or topic. Pro, $9/mo, cancel any time.
This adds $12,500 to the contract. It also extends the substantial completion date to November 6, 2026 and the final completion date to November 20, 2026.
This is a negative change order that reduces the project amount by $74,580.80. It is the final balancing change order for the project.