In plain English
The board will consider awarding two bids for the La Colina Substation Upgrade Project. The bids are for packager materials to Graybar for 472574.85 dollars and for power pits to Procast Products Inc. for 109196.25 dollars. The board will also consider raising the work order budget from 12997400 dollars to 13797400 dollars using the electric fund.
Why it matters: This affects the cost and progress of electric infrastructure upgrades that serve city residents.
Places mentioned: La Colina Substation
Explain it in more detail
Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.
Nov 17, 2026 City Council
The city will add $84,279.45 to its agreement with Rhome Construction Corporation. The new maximum amount is $810,674.45 paid from the Storm Drain Fund. The work is for a modular structure at the Storm Drain Maintenance Building...
utilitiescontracts
Nov 9, 2026 Board of Public Utilities
The board will reject the bid from Servitek Electric, Inc. as non-responsive. They will award Bid 8273 to International Line Builders, Inc. of Corona for $934,383.27 for the Hunter Substation Circuits 21 and 22 4kV to 12kV...