Award bid for Hunter Substation project

Riverside, CAMonday, November 9, 2026utilitiescontracts

In plain English

The board will reject the bid from Servitek Electric, Inc. as non-responsive. They will award Bid 8273 to International Line Builders, Inc. of Corona for $934,383.27 for the Hunter Substation Circuits 21 and 22 4kV to 12kV Make-Ready Project, Phase 2. They will also approve a work order for a total capital expenditure of $2,204,845.99 from the Public Utilities Electric Fund.

Why it matters: This affects costs and improvements to the city's electric power system paid for by the electric fund.

Original agenda text

Reject bid submitted by Servitek Electric, Inc., Norwalk, as non-responsive - Award Bid 8273 to International Line Builders, Inc., Corona, for $934,383.27 for Hunter Substation Circuits 21 and 22 4kV to 12kV Make-Ready Project, Phase 2 - Approve Work Order 2614695 for total capital expenditure of $2,204,845.99 from Public Utilities Electric Fund Capital Account for design, construction, construction support, contract administration, inspection, and construction change order authority costs for Hunter Substation Circuits 21 and 22 4kV to 12kV Make-Ready Project, Phase 2

Exactly as published by Riverside · File 26-3500 · DISCUSSION CALENDAR · Agenda item 22.

Explain it in more detail

Get a deeper walk-through: what this item does, who it affects, what the jargon means, and questions you could ask at the meeting.

Go Pro

Get an email the day Riverside posts an agenda that mentions your street or topic. Pro, $9/mo, cancel any time.

Or start with one free weekly alert

Related items in Riverside

Nov 17, 2026 City Council

Amendment for storm drain maintenance building

The city will add $84,279.45 to its agreement with Rhome Construction Corporation. The new maximum amount is $810,674.45 paid from the Storm Drain Fund. The work is for a modular structure at the Storm Drain Maintenance Building...

utilitiescontracts
Nov 9, 2026 Board of Public Utilities

Bids and budget increase for La Colina Substation Upgrade

The board will consider awarding two bids for the La Colina Substation Upgrade Project. The bids are for packager materials to Graybar for 472574.85 dollars and for power pits to Procast Products Inc. for 109196.25 dollars. The...

utilitiescontracts